Advertisement
100% x 90

Week Calculator

Calculate the exact number of weeks and days between two dates with ISO 8601 week numbers

Calculate Weeks Between Dates

Date from which you would like to count weeks

Date until which you would like to count weeks

By default, the starting day is not included in the counting

Quick Calculation Guide

Step 1: Count the days between the two dates

Step 2: Divide the number by 7

Step 3: Round down to get weeks, remainder is extra days

Example: 23 days รท 7 = 3 weeks + 2 days

Example Calculation

Project Timeline Example

Start Date: January 1, 2024 (Monday)

End Date: March 15, 2024 (Friday)

Total Days: 74 days

ISO Week Start: 2024-W01

ISO Week End: 2024-W11

Calculation

74 days รท 7 = 10 weeks + 4 days

Result: 10 weeks, 4 days

Duration: 2 months, 2 weeks, 4 days

Advertisement
100% x 250

Week Numbering Standards

ISO 8601 Standard

Monday is first day, Week 1 contains January 4th

US Standard

Sunday is first day, Week 1 contains January 1st

Middle East

Saturday is first day of the week

Week Facts

๐Ÿ“…

A year has 52 weeks plus 1-2 extra days

๐Ÿ—“๏ธ

Leap years have 52 weeks + 2 days (366 days)

๐Ÿ“†

Normal years have 52 weeks + 1 day (365 days)

โฐ

Some years have 53 ISO weeks

Understanding Week Calculations

How Week Counting Works

Week calculation involves determining the number of complete 7-day periods between two dates. The result shows both full weeks and any remaining days that don't form a complete week.

ISO 8601 Week Numbering

  • โ€ขMonday is considered the first day of the week
  • โ€ขWeek 1 is the week containing January 4th
  • โ€ขWeek numbers range from 1 to 53
  • โ€ขThursday determines which year the week belongs to

Common Use Cases

  • ๐Ÿ“ŠProject Planning: Calculate project duration in weeks
  • ๐Ÿ’ผPayroll: Calculate pay periods and work weeks
  • ๐Ÿ“šEducation: Academic semester and term planning
  • ๐ŸฅMedical: Treatment schedules and gestation periods

Tip: Use the "include starting date" option when counting inclusive periods, such as vacation days or project timelines where the start date is part of the duration.

Calculation Formula

Total Days = (End Date - Start Date) + (Include Start ? 1 : 0)

Weeks = Floor(Total Days รท 7)

Remaining Days = Total Days mod 7

Advertisement
100% x 250