PERT Calculator

Calculate project completion times using Program Evaluation and Review Technique

Calculate PERT Estimates

days

Everything goes perfectly

days

Normal conditions with some delays

days

Everything goes wrong

days

For probability analysis (leave empty to skip)

PERT Analysis Results

PERT Estimate
10.00 days
Expected completion time
Standard Deviation
1.67 days
Uncertainty measure

Formula: PERT = (O + 4M + P) / 6

Standard Deviation: SD = (P - O) / 6

Analysis Insights

Example: Building a Fence

Project Scenario

Project: Build a fence around property

Optimistic (O): 5 days (perfect weather)

Most Probable (M): 7 days (some weather delays)

Pessimistic (P): 9 days (worst weather)

PERT Calculation

PERT = (5 + 4×7 + 9) / 6

PERT = (5 + 28 + 9) / 6 = 42 / 6 = 7 days

SD = (9 - 5) / 6 = 4 / 6 = 0.67 days

PERT Time Estimates

O

Optimistic

Best-case scenario where everything goes perfectly

M

Most Probable

Most likely scenario with normal conditions

P

Pessimistic

Worst-case scenario with maximum delays

PERT Benefits

More accurate time estimates

Accounts for uncertainty

Better project planning

Risk assessment capability

Statistical foundation

Industry standard method

Understanding PERT (Program Evaluation and Review Technique)

What is PERT?

PERT (Program Evaluation and Review Technique) is a project management tool used to estimate task durations and project completion times. It was originally developed by the U.S. Navy for the Polaris missile program in the 1950s.

How PERT Works

  • Uses three time estimates to calculate expected duration
  • Weighted average gives more importance to most likely estimate
  • Provides statistical measures of uncertainty
  • Enables probability analysis for deadlines

PERT Formulas

Expected Time:

E = (O + 4M + P) / 6

Standard Deviation:

σ = (P - O) / 6

Z-Score:

Z = (D - E) / σ

When to Use PERT

  • Complex projects: With high uncertainty
  • New activities: Limited historical data
  • Critical deadlines: Need probability analysis
  • Risk assessment: Understanding variability

Note: PERT assumes a beta distribution for activity durations and is most effective when time estimates are made by experienced professionals.

PERT vs Other Estimation Methods

PERT

  • • Three-point estimates
  • • Statistical foundation
  • • Uncertainty quantification
  • • Best for uncertain projects

Single Point Estimate

  • • One time estimate
  • • Simple and quick
  • • No uncertainty measure
  • • Best for routine tasks

Historical Data

  • • Past performance
  • • Data-driven approach
  • • Limited to similar tasks
  • • Best for repeated projects